Tuesday, March 18, 2014

CLT panels flying on the GL framing





After four days of actual work on the job site the CLT deck on top of the GL framing is almost done. The X-shaped steel bracing system is already in position, waiting to be tightened. All the CLT panels will be connected to the GL beams from the top (no needs to install scaffolds underneath); the panels are also connected toghether by using couples of inclined screws (partial thread and full thread).

Thursday, March 13, 2014

Installing GL beams

...after a delay waiting for the crane, installation of GL beams started









Sunday, March 9, 2014

Shipment arrived

Here we are!




The BBS panels, GL columns and beams  are now at the site. Assembly to start soon..


Wednesday, March 5, 2014

Ermanno and Werner working on the tracing for the GL columns at the site



CLT panels and Glulam columns and beams expected to be unloaded on site on Friday March 7th - Installation to begin right after unloading is complete. Material imported from Binderholz and supplied by New York based HolzBuild inc.

These 2 images are from the Revit model used to prepare the shop drawings